Project Timeline
Start of Public Consultation
Pre-application meetings with Reading Borough Council
Started May 2019 – ongoing
One to One Meetings
Started April 2019 – ongoing
Meetings with local residents, Associations, Businesses and Community Groups.
First Public Exhibition
25th and 26th September 2019
Share our emerging proposals and reflect on public opinion to guide design proposals.
Second Public Exhibition
End of October/Early November 2019
View our final proposal prior to the application being submitted to RBC.
Planning Application Submission
End of February 2020
Formal outline planning application submitted to Reading Borough Council.
Planning Application Decision
Autumn/Winter 2020
Outline planning application decision by Reading Borough Council Planning Committee. Due to the current circumstances this is likely to change.